Erection in progress of the LIMESTONE HANDLING SYSTEM, Coal Fired Power Plant 3×140 MW, Babelan, Indonesia.
The plant is designed and built by OM Siderurgica for the Limestone handling and it is divided in 6 main activities:
1 -LIMESTONE RECEIVING, STOCKING AND SCREENING
2- LIMESTONE RECLAIMING
3- RAW LIMESTONE STORAGE
4- CRUSHING & CLASSIFYING
5- TREATED LIMESTONE STORAGE
6- PNEUMATIC TRANSPORT